The Circuitry
THE CIRCUITRYYour one-stop source for all tech news
  • Today
  • Feed
  • Events
  • Saved
HOMETODAYFEEDEVENTS
BOOKMARKS
RSS
© 2026 The Circuitry
About UsSourcesContactCorrectionsPrivacy
  • Today
  • Feed
  • Events
  • Saved
  • AAPL
  • MSFT
  • GOOGL
  • META
  • NVDA
  • TSLA
  • AMZN
  • INTC
  • SONY
  • TTWO
  • COIN
  • BTC
  • ETH
  • SOL
  • AAPL
  • MSFT
  • GOOGL
  • META
  • NVDA
  • TSLA
  • AMZN
  • INTC
  • SONY
  • TTWO
  • COIN
  • BTC
  • ETH
  • SOL

Feed

Ad
From The CircuitryVerified tech news, cross-checked.How we verify →
  • Boom fires its Superpower engine core for the first timeEnergy
  • Meta is re-evaluating its 2030 net-zero emissions goalEnergy
  • SBM Offshore will build the Longtail FPSO for ExxonMobil GuyanaEnergy
  • U.S. energy storage capacity has passed 200 GWhEnergy
  • PJM is filing a plan to cut interconnection studies from two years to oneEnergy
  • Eldridge-led group agrees to buy Lukoil's overseas energy assetsEnergy
  • ConocoPhillips agrees to sell its Norway business for $4.425 billionEnergy
  • IEA says the oil market returns to a surplus this quarterEnergy
Scroll for more
Verification
VERIFIEDConfidence: HIGH
Source identified
Claims cross-referenced
No discrepancies found
Sourcing
1source
Ad
From The CircuitryWhy The Circuitry

Verified tech news, cross-checked.

Every story is checked against independent sources before it posts — no rumors dressed up as fact.

How we verify →
From The CircuitryWhy The Circuitry

Verified tech news, cross-checked.

Every story is checked against independent sources before it posts — no rumors dressed up as fact.

How we verify →
Home/Energy/Statnett pauses new data-center grid reservations until 2027
VERIFIEDBy Xavier Rivera·Monday, November 9, 2026 at 8:11 PM AST·2 min read

Statnett pauses new data-center grid reservations until 2027

Statnett said it is pausing new grid-capacity reservations and new technical approvals for data centers, and that the pause is expected to end by August 1, 2027 at the latest.

Source:Statnett
Post
Statnett pauses new data-center grid reservations until 2027
Ad
From The CircuitryVerified tech news, cross-checked.How we verify →
Ad
From The CircuitryWhy The Circuitry

Verified tech news, cross-checked.

Every story is checked against independent sources before it posts — no rumors dressed up as fact.

How we verify →
TL;DRAI · 60 sec read

Norway's grid operator Statnett said it is pausing new connection reservations and new technical approvals for data centers. It said the pause is expected to be lifted by August 1, 2027 at the latest, and that projects with approved functional requirements can still connect.

Statnett said it is pausing new grid-capacity reservations for data centers, and pausing work on new applications to approve how those facilities behave on the grid. The Norwegian system operator said the stop is expected to be lifted by August 1, 2027 at the latest.
Statnett said the temporary stop is expected to be lifted by August 1, 2027 at the latest.
The pause covers new reservations and new approvals. Statnett said the measures are a temporary stop on new connection reservations, and a temporary stop on processing new applications for approval of facility functionality under the system-responsibility rules. It also said it is stopping work on applications already received for facilities that would connect directly to the 420 kilovolt grid. It said the measures cover large customers with an unusual demand profile, typically data centers.
From The CircuitryThe Feed — live briefs across tech, all day.See what’s happening →
Approved projects can still connect. Statnett said the decision is not a general stop on connecting data centers. Facilities that have already had the required functional requirements approved can still connect. Existing connections are not affected. Applications already in process for regional-grid connections with a near-term start date will not be stopped. Statnett said it will also consider taking some applications for smaller facilities planned before August 1, 2027.
It said 800 megawatts of data-center load are connected today, and that 4,200 megawatts already have reserved capacity.
The queue is larger than today's peak demand. Statnett said 800 megawatts of data-center load are connected today, and that 4,200 megawatts already have reserved capacity. It said 9,100 megawatts are in the capacity queue, and that requests for a further 18,000 megawatts are on file. It said Norway's maximum power use is a little over 25,000 megawatts.
Ad
From The CircuitryWhy The Circuitry

Verified tech news, cross-checked.

Every story is checked against independent sources before it posts — no rumors dressed up as fact.

How we verify →
The operator said it needs new rules first. Peer Olav Østli, executive vice president for system operation and markets, said the pause is needed so Statnett can put tools and a framework in place. The notice said new functional requirements will go out for comment and must be approved by the energy regulator RME. It said capacity freed by the pause will not be given to other customers ahead of data centers already in line.
Why this mattersAI · ~100 words

Tap a lens to see what this story means for you.

Morning Brief

Liked this? The Brief brings you the whole day in tech, verified, every morning.

Two minutes, free forever. What's in The Brief →

Reader-supported
DonateBuy me a coffee →Follow@thecircuitry_ →Follow@thecircuitry.to →
HELP US IMPROVE
From The Circuitry

See what’s happening right now

The Feed runs all day — short, verified briefs the moment they break.

Open the Feed →
From The Circuitry

Follow @thecircuitry_

Every story we publish, as it happens. No noise between.

Follow on X ↗On Bluesky ↗

Reader-supported

The Circuitry is a passion project I've always wanted to build, and I love the work behind it.

Running it costs real money. APIs, hosting, time. To keep improving the site and growing this into something useful for everyone, those costs have to be covered.

Any contribution is appreciated. If not, no pressure. Thanks for reading.

Buy me a coffee
energydatacenternorway
More inEnergy
  • Eldridge-led group agrees to buy Lukoil's overseas energy assets

    Energy · 2d
  • ConocoPhillips agrees to sell its Norway business for $4.425 billion

    Energy · 5d
  • IEA says the oil market returns to a surplus this quarter

    Energy · 14d
SupportThe Work

The Circuitry is reader-supported. If you find the daily brief useful, you can buy me a coffee to keep it going.

Buy a coffee →
Ad
From The CircuitryWhy The Circuitry

Verified tech news, cross-checked.

Every story is checked against independent sources before it posts — no rumors dressed up as fact.

How we verify →
From The CircuitryWhy The Circuitry

Verified tech news, cross-checked.

Every story is checked against independent sources before it posts — no rumors dressed up as fact.

How we verify →

MORE IN THIS BEAT

All Energy →
  • Energy·Nov 22

    Boom fires its Superpower engine core for the first time

    Boom has fired the prototype core of its Superpower engine for the first time, in a Nov. 21 test east of Denver. The core is meant for a 42-megawatt gas turbine for data centers, with a fully integrated engine test aimed at the middle of next year.

  • Energy·Nov 20

    Meta is re-evaluating its 2030 net-zero emissions goal

    Meta is re-evaluating the 2030 timeframe for its net-zero emissions goal and its near-term intensity targets. Long-term ambitions are unchanged, and the company has contracts for more than 30 GW of clean and renewable power.

  • Energy·Nov 17

    SBM Offshore will build the Longtail FPSO for ExxonMobil Guyana

    SBM Offshore has been awarded contracts to construct and install the Longtail FPSO for ExxonMobil Guyana. The vessel is designed for 250,000 barrels of condensate a day, with gas processing of 1.2 billion standard cubic feet each day.

  • Energy·Nov 17

    U.S. energy storage capacity has passed 200 GWh

    U.S. energy storage capacity has passed 200 GWh after 48.3 GWh of installations in the first nine months of 2026. Those additions are up 20% from a year earlier, and the industry outlook now expects 708 GWh online by 2030.

  • Energy·Nov 16

    PJM is filing a plan to cut interconnection studies from two years to one

    PJM has developed a plan to cut the study time for new generation and large-load transmission service from two years to one. The operator is filing it with federal regulators at the end of the day on November 16.